New Keefer Crossing Middle School and Comprehensive HS #3 Updates
 
Forum Image
 
Updated 9.28.2020
 
Keefer Crossing Middle School site paving is 80 percent complete. The structural steel is 95 percent complete, masonry is 20 percent complete, storm and sewer site utilities are 95 percent complete and the rough mechanical and electrical installation is 18 percent complete.
 
Site clearing for Comprehensive High School #3 is 95 percent complete. Rough grading is 55 percent complete. The foundation pad is 100 percent complete and the general contractor is scheduled to start drilling piers this month.
* Reactions disabled on political threads.
What are your thoughts? Log in or sign up to comment
ROS Top




SPONSORED:
Fountain View Farm Weddings & Event Venue Logo Thrive Nutrition Company Logo Kingwood Perfect Smiles Logo The Bath Program Logo Abstract Jiu Jitsu Logo Kingwood Tire and Auto Logo Primrose School of Kingwood at Oakhurst Logo Calimax Auto Sales Logo Kenneth's Car Care Logo The Village Thrift Shop Logo
Sponsor an Ad »



See more of PorterTX.com by logging in
Your online community neighborhood for Porter-area residents.
Kosmin Media